STOPPLE PROCEDURES
STOPPLE PROCEDURES
1. All STOPPLE Fittings Should Be Attached Prior To The Arrival Of TDW Services.
2. Meet With Customer.
- Discuss job with man in charge to assure a complete understanding of what is to be accomplished.
- Verify line contents, pressure, temperature, pipe wall thickness, direction of flow and flow rate.
- Inventory TDW equipment, check to be sure no damage has occurred in shipment.
3. Check Lock-O-Ring Flange On The STOPPLE Fittings.
- Extend and retract segments to make sure they work freely and count and record turns required to operate.
- Clean bore of fitting and flange face.
- Build support beneath fitting to support weight of equipment.
- Check gaskets so that no part will extend into bore of fittings.
4. Install TDW Sandwich Valve.
- Turn valve in horizontal position and rig from all four lifting eyes so that valve will be parallel to face of flange on fitting.
- Raise valve off ground and open. Leave valve open.
- Clean valve face.
- Install gasket.
- Lower valve onto fitting slowly, keeping studs free in flange bolt holes. Watch for possible gasket damage and make sure the gasket does not extend into the bore.
- Align bore of valve with bore of fitting.
- Install nuts and tighten evenly.
- Extend and retract segments again to make sure they operate freely.
- Install gasket on top of valve.
5. Install 2-in. Equalization/Purge Valve On Thread-O-Ring Fitting.
- Check Thread-O-Ring Fitting for cleanliness.
- Check valve for full 2-in. bore and operation.
- Install valve using thread tape or compound and leave valve open.
6. Make 2-in. Equalization/Purge Hot-tap.
- Assemble drill and 2-in. threaded adapter to T-101.
- Install T-101 on valve and install bleeder valve in machine.
- Perform pressure test. Test pressure to be determined by customer.
- Perform hot tap.
- Open bleeder valve to relieve pressure and remove machine.
7. Assemble Hot-Tapping Machine.
8. Make STOPPLE Plugger Hot-tap.
- Install tapping machine on TDW Sandwich Valve and tighten flange bolts evenly.
- Fitting and al joints below valve must be tested before starting tap. Test pressure to be determined by customer.
- Connect hydraulic hoses from power unit to tapping machine for air line from air compressor for air driven machines.
- Perform hot tap.
- Close sandwich valve.
- Relieve trapped pressure through bleeder valve.
- Remove tapping machine from Sandwich valve.
9. Install STOPPLE Sealing Element.
- O.D. of leading edge of sealing element must correspond with pipe I.D.
10. Install STOPPLE Plugging Machine.
- Install new gasket.
- Install STOPPLE Plugging Machine on Sandwich valve.
- Receive permission to set STOPPLE.
- Open Sandwich valve.
- Set the STOPPLE Plugging machine.
11. Relieve Pressure In The Isolated Section Of Line.
- After the plugging machine is set and locked into place, pressure can be relieved through the blow down connection.
- It can be determined at this point if STOPPLE Plugging Machine is holding.
- If not, may be necessary to equalize pressure in line, retract plugging machine, and change sealing element.
12. Customer To Make tie-ins, Repair, Or Installation Of New Piping.
13. Equalize Pressure The Isolated Pipe Section.
- Connect high pressure hose or piping from the STOPPLE Plugging Machine to the equalization connection on the isolated section.
- Purge air from the equalization connection.
- When air is purged, close equalization valve, and pressure will equalize.
14. Retract STOPPLE Plugging Head.
- When pressure is equalized, leave 2-in. valve on plugging machine and 2-in. connection on line open.
- Raise STOPPLE Plugging Head.
- Close Sandwich Valve.
- Close 2-in. Valve on line, but leave 2-in. valve on STOPPLE Housing open.
- Open bleeder valve to relieve trapped pressure.
15. Remove STOPPLE Plugging Machine.
- Remove bleeder valve and 2-in. valve from STOPPLE Housing.
- Remove plugging machine from Sandwich Valve.
16. Attach The Lock-O-Ring Plug On The Tapping Machine.
17. Install Lock-O-Ring Plug In The Lock-O-Ring Flanged Fitting.
- Install Tapping machine on Sandwich Valve.
- Open Sandwich valve.
- Install Lock-O-Ring Plug in flange.
- Remove tapping machine from Sandwich Valve.
- Remove sandwich valve.
- Install blind flange and tighten bolts evenly.
18. Install 2-in. Thread-O-Ring Completion Plug.
- Install plug holder and 2-in. threaded adapter on T-101.
- Install plug on plug holder.
- Install T-101 on 2-in. valve.
- Open 2-in. valve.
- Install Thread-O-Ring plug into fitting.
- Remove T-101, remove valve, and install 2-in. high pressure pipe cap.
19. Repackage All Equipment Properly And Securely For Return Shipment.
<%=company%>