Case Study

Emek Hefer - Cowshed Waste Water Treatment

Source: GES - Global Environmental Solutions

Click Here To Download:
Case Study: Emek Hefer – Cowshed Waste Water Treatment

  • A regional cowshed manure bio-gas-plant, first of its kind in Israel.
  • The plant treats about 600 ton of cowshed manure per day with anaerobic digestion technology and energy production.
  • The plant produces 2 MW of green electricity.
  • BOOT contract for 20 years.

Objective:

  • To find a technological and financially feasible solution for cowshed waste (from local collection pits) at Emek Hefer region, Israel.
  • Strict regulations imposed by local authorities to minimize contamination caused by traditional cowshed design and construction made a new approach mandatory.

Click Here To Download:
Case Study: Emek Hefer – Cowshed Waste Water Treatment

SOURCE: GES - Global Environmental Solutions